construction estimate

69420 S. hairball Trail
Prescott, AZ   86203
(928)911-2321

Terms of Agreement for Written Estimate

2300 Square feet of tear up---Padding and carpet
24 man hours @ 45 per hour           $1,080.00
Disposal fee                             $200.00
New carpet customer choice $26.00/sq.ft.-2300 Sq/Ft                       $59,000.00
3/8 Padding is $6.00/sq.ft.-2300 Sq/Ft                       $13,800.00
Labor 16 man hours @ $60.00/hour               $960.00
+15% for materials         $10980.00
Sub total         $75,040.00
Tax @ 8%           $6,003.20
Total         $81,043.20
    This estimate includes Clearing and putting back in same spot work area, old carpet removal, all tools used in job, and clean up.   Any add on would be estimated as other work to be performed and priced appropriately.   Need ½ down payment to begin work listed above. The rest at time of completion.
By signing below, you agree to the terms of this estimate and agreement.